All Systems GO!

Image
Just got the call - Weather permitting we are go for site cut next week, 17/10/2022. Frank the Site Super is going to Text me when they have the machine onsite and I'll pop up and have a look.  

Scheduling order - slab and retaining wall

Our Site Supervisor has met the retaining wall contractor onsite this afternoon. The order of activities has been sorted. The site will be cut and the slab poured first. While the slab is curing, the retaining wall will be constructed. The site will then be handed back to the builder and the rest of the house will be built. No date yet on the excavations as the weather has turned nasty so there is every chance of a delay. 

We have a Port-a-Loo 20_09_2022

Image
Some more movement at the site. We have a Port-a-Loo!   

Off and Running! Site Fence erected and Peg Out

Image
Some movement onsite today. The Site Fencing is now in place and the Surveyor was onsite doing the initial peg out.   

Hornsby Shire Council - CDP/976/2022 Complying Development Certificate

Image
All documents have been lodged with Hornsby Council and the SECTION 7.12 PAYMENT ADVICE, and the  Asset Damage Inspection Fee have been received and paid. Just waiting on the Bank documentation detailing  Letter of Authority to Commence Construction (LACC) also known as Letter of Commencement.  The LACC details:  Confirmation of the funds available for drawdown; Confirmation from the bank that they have received all information required; and Confirmation from the bank that they are ready to drawdown on the loan facility upon receipt of progress claims. We have also received the quote from Kuring-Gai Civil whom are building the Retaining Wall. The quote will be accepted and will be incorporated in the build.

CDC Approval Received

Today is a big day! We received CDC approval from the Private Certifier.   

Site Safety Fencing

Just got an email from the builder that they are preparing to install the site fencing. CDC Approval is not far off apparently.