Scheduling order - slab and retaining wall

Our Site Supervisor has met the retaining wall contractor onsite this afternoon. The order of activities has been sorted. The site will be cut and the slab poured first. While the slab is curing, the retaining wall will be constructed. The site will then be handed back to the builder and the rest of the house will be built. No date yet on the excavations as the weather has turned nasty so there is every chance of a delay. 

Comments

Popular posts from this blog

Builder # 2 Sketches / Layout / External and Internal Views

Starting Over

Plans 2.0