Retaining wall - Phase 2 - 3/2/2024

Onto the next part - Phase 2 of the Retaining Wall. This will create the platform and support the digging of the pool. Got a few servcies (storm water and sewer) to take care of which wont be too hard. Footings down by Tuesday, blocks in by Thursday, and core filled by Friday.







Comments

Popular posts from this blog

Plans 2.0

Builder # 2 Sketches / Layout / External and Internal Views