Retaining wall - Phase 2 - 3/2/2024

Onto the next part - Phase 2 of the Retaining Wall. This will create the platform and support the digging of the pool. Got a few servcies (storm water and sewer) to take care of which wont be too hard. Footings down by Tuesday, blocks in by Thursday, and core filled by Friday.