Sub Floor - progress pics of install. 29/5/2023

Image
  Feeling more and more like a house everyday.  

Sub Flooring and second level frames - Ready to go!

Image
Scaffolding completed during the week and the sub flooring is ready for install. Carpenters primed and ready to roll on Monday, 29/5 to stand and fix-off the second level.

2nd Level Scaffolding 19/5/2023

Image
Moving right along the 2nd Level Scaffolding has commenced.    

Lower Level Bricks completed 12/5/2023

Image
Lower level brickwork wrapped up today. Next phase is subfloors, upstairs framing and roof trusses.

Day 3 of Bricks 10/5/2023

Image
The Bricklayers are powering along

Lower Level Framing completed and Windows installed 4/5/2023

Image
Progressing along, the lower level framing has been completed and windows installed. The Bricklayer is starting tomorrow.