Posts

Pool shell, filter, pump, and heater installed.

Image
Been a busy time of late with plenty happening in the backyard.The pool shell has been poured, along with the pool filter, pump, and heater installed.

Pool ready for concreting

Image
Steel and plumbing complete. Ready for concrete next Tuesday 2/4/2024.   

Lots happening - Pool excavation and moving in 15/3/2024

Image
Big push yesterday in prep for the moving truck to move all the big pieces of furniture. They did a great job and didnt damage any of our stuff or any walls in the new house.  The pool excavation was going great until we hit an old septic tank. Had to arrange for a separate skip to dispose of it. After that is was smooth sailing and the dig is now complete.   

Keys Keys Keys!!!!!

Image
Big Day today. I'll post some pics of the completed house shortly.  

Retaining Wall Bagging complete 15/2/2024

Image
Big job ticked off the list. The backyard is now ready for the pool contractor. 

Retaining Wall 5/2/2024 - 8/2/2024

Image
With the services pipe issue solved early this morning, the guys smashed it out in the heat today. Starter bars, trench mesh, and the pour of the footings. The placement of the wall will net us around another 27sqm of land. Worth the effort and the expense.